The project consisted of an addition to the existing chilled water plant to house the mechanical equipment. Installation included two 900 ton centrifugal chillers with variable frequency drives, two 900 ton cooling towers with variable frequency drives, two new primary chilled water pumps, and three new condenser water pumps. The plant was designed to allow installation of a future thermal storage system.
The plant addition included installation of a second 8,500 gallon indoor sump below grade to create a second condenser water system and to allow simultaneous use of the plate and frame heat exchanger on one condenser water system and the chillers on the other condenser water system.